FINAL UPDATE by FDOT regardiing defaulted District 7 road projects
Roadway |
Fri - December 17, 2021
4:48 pm
|
Article Hits:285
| A+ |
a-
December 17, 2021
Florida Department of Transportation (FDOT)
District 7, West Central Florida: Citrus, Hernando, Hillsborough, Pasco, and Pinellas counties
Status update of defaulted FDOT projects due to bankruptcy of D.A.B. Constructors of Inglis, Florida:
PROJECT T7383 - CITRUS COUNTY, FLORIDA
Widening of U.S. 19, from W. Green Acres St. to S. Jump Court, in Homosassa (2.1 miles)
• Preliminary work (project submittals and coordination) began this week, and regular contract work is expected to begin January 3, 2022.
• Nelson Construction is the Completion Contractor for the project.
• The Department’s representatives are sampling and tracking turbidity readings at the Pond 4 outfall as well as sample points at the right-of-way in conjunction with T7407. This week, all the test results are meeting water quality requirements. Currently, no discharge is leaving Pond 4.
• This is the final update for this project. See FDOT website for updates on this project, as work is currently progressing: www.fdottampabay.com/project/110/405822-2-52-01.
PROJECT T7388 - PASCO COUNTY, FLORIDA
Widening of S.R. 54, from Curley Road to Morris Bridge Road, in Zephyrhills (4.5 miles).
• Western Surety Company and completion contractor
• Cone & Graham Inc. are continuing to finalize the completion contract.
• Cone & Graham has submitted its erosion control plan to FDOT and Southwest Florida Water Management District (SWFWMD).
• Highway Safety Devices will be installing additional traffic detection at the Meadow Pointe Blvd. and S.R. 54 intersection
• Department representatives continue filling potholes and maintaining traffic control devices throughout the project.
• This is the final update for this project. See FDOT website for updates on this project, as work will begin again Monday, December 20, 2021: www.fdottampabay.com/project/212/416561-2-52-01.
PROJECT T7407 - CITRUS COUNTY, FLORIDA
Widening of U.S. 19, from W. Jump Court in Homosassa to W. Fort Island Trail, in Crystal River (4.7 miles)
• See FDOT website for updates on this project, as work is currently progressing:
www.fdottampabay.com/project/240/405822-3-52-01.
PROJECT T7445 - CITRUS COUNTY, FLORIDA
Resurfacing of U.S. 19, from the Hernando County Line to W. Green Acres St., in Homosassa (3.8 miles)
• See FDOT Website for updates on this project, as work is currently progressing: www.fdottampabay.com/project/300/437514-1-52-01.
PROJECT T7433 - PASCO COUNTY, FLORIDA
Widening of S.R. 52, from Suncoast Parkway to U.S. 41, in Land O' Lakes (3.8 miles).
• See FDOT website for updates on this project, as work is currently progressing: www.fdottampabay.com/project/266/256323-1-52-01.
PROJECT T7412 - PASCO COUNTY, FLORIDA
The Diverging Diamond Interchange ("DDI") on S.R. 56 at I-75 in Wesley Chapel.
• See FDOT website for updates on this project, as work is currently progressing: www.fdottampabay.com/project/262/430573-1-52-01.
PROJECT T7402 - HILLSBOROUGH COUNTY, FLORIDA
Widening of C.R. 580 (Sam Allen Road) from S.R. 39A (Paul Buchman Highway)
to Park Road in Plant City (2 miles).
• See FDOT website for updates on this project, as work is currently progressing: www.fdottampabay.com/project/233/257862-3-52-01.