FDOT District 7 update of defaulted road projects, Dec. 10, 2021
Roadway  |  Sat - December 11, 2021 12:08 am  |  Article Hits:307  |  A+ | a-
Florida Department of Transportation (FDOT) 

District 7, West Central Florida: Citrus, Hernando, Hillsborough, Pasco, and Pinellas counties

Status update of defaulted FDOT projects due to bankruptcy of D.A.B. Constructors of Inglis, Florida:

PROJECT T7383 - CITRUS COUNTY
Widening of U.S. 19, from W. Green Acres St. to S. Jump Court, in Homosassa (2.1 miles)
    • The Takeover Agreement is complete and was received by the Department for execution on December 10, 2021.  A preconstruction meeting is being held on Tuesday, December 14, 2021 with the completion contractor, Nelson Construction.  Preliminary work is expected to begin December 15, 2021, and regular contract work is expected to begin January 3, 2022.
    • The Department’s representatives are sampling and tracking turbidity readings at the Pond 4 outfall as well as sample points at the right-of-way in conjunction with T7407 (the widening of US 19 from Jump Court in Homosassa, FL to Fort Island Trail in Crystal River, FL). This week, all the test results are meeting water quality requirements. Currently no discharge is leaving Pond 4.

PROJECT T7407 - CITRUS COUNTY
Widening of U.S. 19, from W. Jump Court in Homosassa to W. Fort Island Trail, in Crystal River (4.7 miles)
    • See FDOT website for updates on this project as work is currently progressing:
fdottampabay.com/project/240/405822-3-52-01.

PROJECT T7445 - CITRUS COUNTY
Resurfacing of U.S. 19, from the Hernando County Line to W. Green Acres St., in Homosassa (3.8 miles)
    • See FDOT Website for updates on this project as work is currently progressing:
fdottampabay.com/project/300/437514-1-52-01.

PROJECT T7388 - PASCO COUNTY
Widening of S.R. 54, from Curley Road to Morris Bridge Road, in Zephyrhills (4.5 miles).
    • Western Surety Company and completion contractor Cone & Graham Inc. are continuing to finalize the completion contract.  Cone & Graham is putting together erosion control plan and project schedule.  They are expected to mobilize to restart work on Monday, December 20, 2021.
    • Southern Precision has continued mowing and litter removal this week.
    • Highway Safety Devices are scheduled to return to the SR 54 Meadow Pointe Blvd. intersection to improve traffic detection on Monday, December 13, 2021. 
    • Department representatives continue to maintain traffic control devices throughout the project.

PROJECT T7433 - PASCO COUNTY
Widening of S.R. 52, from Suncoast Parkway to U.S. 41, in Land O' Lakes (3.8 miles).
    • See FDOT website for updates on this project as work is currently progressing:
www.fdottampabay.com/project/266/256323-1-52-01.

PROJECT T7412 - PASCO COUNTY
The Diverging Diamond Interchange ("DDI") on S.R. 56 at I-75 in Wesley Chapel.
    • See FDOT website for updates on this project as work is currently progressing:
fdottampabay.com/project/262/430573-1-52-01.

PROJECT T7402 - HILLSBOROUGH COUNTY
Widening of C.R. 580 (Sam Allen Road) from S.R. 39A (Paul Buchman Highway)
to Park Road in Plant City (2 miles).
    • See FDOT website for updates on this project as work is currently progressing:
fdottampabay.com/project/233/257862-3-52-01.
 